Project Name:12000BPH Bottled Water Production Line Project in Yemen
In January 2023, Mr. Khaled contacted SinoPAK TEC through our partner in Yemen. As this was the client’s first venture into the water bottling industry, they had little knowledge of production lines. However, after careful discussions with our Yemeni partner and reviewing one of our production lines in Yemen, the client was impressed with our equipment and its performance.
The client required a fully automated, high-quality production line capable of producing 12,000 bottles per hour to meet their market needs.
After multiple phone discussions to understand the client’s requirements, we assured them of the best after-sales service and support, which included sending engineers for installation and commissioning. The client was also reassured by seeing our production lines in operation in Yemen, which confirmed the high quality of our machines and the reliability of our after-sales service. This quickly convinced them to choose SinoPAK TEC.
4.1 Post-Production Dripping:
4.2 Blow Molding Machine – Poor Bottle Formation:
4.3 Hot Melt Labeling Machine – Label Adhesion Issues:
4.4 Film Wrapping Machine – Frequent Film Jamming:
The production line successfully achieved the expected capacity of 12,000 bottles per hour. Our installation and commissioning team ensured all machines were correctly installed, connected the necessary utilities, and provided comprehensive employee training. This helped the client quickly meet market demand. Throughout the project implementation and commissioning phases, our technical team demonstrated a high level of professionalism and efficiency, which was highly appreciated by Mr. Khaled. He expressed great satisfaction with our after-sales support.
Photos of the shipment and the production line in operation.