Project Name:14000BPH Bottled Water Production Line Project in Yemen
In April 2021, Mr. Saif, the owner of a water company in Yemen, contacted SinoPAK TEC with the goal of expanding his production capacity. His existing production line had a capacity of 5000 bottles per hour, but he needed a new facility and a completely new production line to increase output.
The client required a new production line capable of consistently producing 14,000 bottles per hour. The primary goal was to ensure stable operation and high-quality output.
After numerous discussions on WhatsApp, we invited Mr. Saif to visit our factory in China. Impressed by the quality of our machines, Mr. Saif also had the opportunity to visit a production site using our equipment and witness the production process firsthand. He was highly satisfied and requested an identical production line. We assured him that we would install the same high-quality system for his new facility.
4.1 Blow Molding Machine Mold Jamming:
4.2 Hot Melt Labeling Machine – Label Misalignment:
4.3 Palletizer Control System Issues:
4.4 Staff Forgetting How to Change Bottle Size Parts:
The production line successfully reached the targeted capacity of 14,000 bottles per hour, helping Mr. Saif achieve his goal of expanding production capacity. The client was extremely satisfied with our installation and commissioning engineers, even awarding them bonuses as a sign of appreciation for their professional work ethic and successful project delivery.
Photos of the shipment and the production line in operation.